TITLE
Psytalia Waste Water Treatment Facility (Kleps)
OWNER
EYDAP SA
PROJECT
Operation and Maintenance of the Psyttalia Wastewater Treatment Plant
LOCATION
PSYTALIA ISLAND
CONTRACTOR
Joint Venture: Athena Sa – Themeliodomi Sa – Aktor Sa – Technical Companychristoforos D. Constantinidis Sa – Technerga – E. Tsambras Aete
CDC S.A. PARTICIPATION
15%
Description
Provision of specialized scientific and other staff for the operation and maintenance of Biological Water Purification as well as for operational
interventions.
Technical Data
-
- TREATMENT PROVISION: 1.000.000 m3 / day
- OPERATION 60 months:
- Provision of specialized scientific and other staff for the
operation and maintenance of the facility for a period of
39 months
- Provision of specialized scientific and other staff for the
- CONSTRUCTION
-
- Capacity expansion of a pumping station
- Shredder upgrade,
- Dehydrated sludge storage silo,
- Tank sludge scavenger upgrade,
- Administration building 1718 m
-