TITLE: WATER TREATMENT PLANT IN THESSALONIKI
OWNER: EYDE THESSALONIKI
PROJECT: TECHNICAL STUDY – CONSTRUCTION OF THE THERMAL DRYING UNIT OF DEHYDRATED SLUDGE OF EELTH.
LOCATION: INDUSTRIAL AREA OF THESSALONIKI – SINDOS
CONTRACTOR: TECHNICAL COMPANY CHRISTOFOROS D. KONSTANTI
NIDIS SA
CDC S.A. PARTICIPATION: 100%
TYPE OF PROJECT: TECHNICAL STUDY, CONSTRUCTION

Description

PROJECT DESCRIPTION

Technical Study – Construction, assurance of efficient operation and
maintenance for a period of 15 months of the Sludge Thermal Drying
Unit of Thessaloniki Wastewater Treatment Plant and related facilities.

TECHNICAL DATA

The Thermal Drying Unit consists of two parallel drying rotors with
rotating drums with a nominal exhaust capacity per line of 4,000 kg H 2
O per hour in continuous operation and maximum exhaust capacity per
line of 4,600 kg H 2 O per hour for 7 days continuous operation.
Treatment of dehydrated sludge from EELTH. Total quantity of solid
material 58.000kgr DS / nm and dehydrated sludge concentration from
18% to 28%.