TITLE

Chalkida Waste Treatment Plant

OWNER

DEYA CHALKIDA

PROJECT

Technical Study, Construction and Extension of Sewage Treatment Plant in Chalkida

LOCATION

Chalkida

CONTRACTOR

Technical Company Christoforos D. Constantinidis Sa

CDC S.A. PARTICIPATION

100%

Description

Technical Study-Construction of the Processing Plant of the Municipality of Chalkida
The project contains:
(a) submarine pipelines
(b) waste water pre-treatment
c) reception and pre-treatment of sewage
(d) the sewage treatment process is the activated sludge method in
aeration tanks with nitrogen and phosphorus removal and sludge
anaerobic digestion.
Operation and maintenance of the facility for 18 months

Technical Data

  • Designed for 16,000 m3 per day urban waste water, 1600m3 /
    day sewage sludge
  • Equivalent population 60,000